25 MWMithapur, Gujarat, for SBI Caps
20 MWPunjab, listed 2014
5 MWRajasthan, listed 2014
3 statesGujarat, Punjab, Rajasthan

The situation

Banks and financial institutions financing solar plants asked for an independent technical review before lending.

Background

A lender cannot judge a plant's design and construction on its own. A Lender's Independent Engineer (LIE) reviews them and reports the technical risks so that the lender can decide.

What was tested, and how that method works

SgurrEnergy's project pages list lender's technical advisory work with the scope "Lenders Independent Engineer" during financing and bankability.

An LIE reviews design, equipment, contracts, construction progress and test results, walks the site and reports risks and gaps. The review can repeat at construction milestones and at commissioning.

Our service: Engineering, due diligence and LIE →

What was found

  • Examples listed include a 25 MW plant at Mithapur, Gujarat, for SBI Caps, and a 20 MW plant in Punjab in 2014.
  • A 5 MW plant in Rajasthan is also listed, dated 2014.

How it unfolded

FinancingA lender engages an independent engineer.
ReviewDesign, contracts and construction records are checked.
SiteWalkdown and spot verification.
ReportIndependent opinion on technical risk.

Outcome

The pages describe the scope, not findings or results.

Lessons for a plant owner

  • LIE work happens at the financing stage. It tells a lender whether a plant is technically sound.
  • The same review is useful to buyers and owners facing refinancing.
  • Independent tests on site give an LIE opinion more weight than documents alone.

Questions to ask about your own plant

  • Are our design, construction and test records complete and in order?
  • What would a lender flag first about our plant?
  • Do we have commissioning test reports on file?

How we would approach a similar site

We would review design, construction records and test data, and give the lender a clear independent opinion.